Timeline for Kerens to Parsons
To help you understand not only the process but also the schedule for the study of the Corrick's Ford Battlefield segment of Corridor H, below is a timeline developed by the West Virginia Division of Highways.

This timeline illustrates the processes and studies completed as the road progresses. The timeline includes estimated dates for key milestones for the project and the steps necessary to secure of state and federal agencies preserving the historic civil war battlefield.

On the Timeline, there are approximate time periods for Public Information Workshops. These will preserve periodic opportunities for public input as the process proceeds. All public meetings were advertised well in advance, including on this web site, and the results of the meetings will be reported here and through mass media.


Timeline for Kerens to Parsons

April 2000 Notice of Intent published by FHWA
June 2000 The Scoping Process begins, the Eligibility Report identifying historic buildings and structures affected by all alternatives is developed and Public Workshops are organized
September 2000 Public Meeting
October 2001 The Supplemental Draft Environmental Impact Statement is approved
October 2001 Public hearing
December 2001 The Preferred Alternative is identified
October 2002 The Final Environmental Impact Statement is approved and circulated for comment
April 2003 The Amended Record of Decision is approved



top of page

Route | Environment | Culture | Economics | Engineering | Safety | Press | Resource | Home
email us your comments or questions
Copyright © 2003 Corridor H, West Virginia Division of Highways. All Rights Reserved.