Elkins Construction Site Tour
The following is a photo tour from June 2001 of the construction on the Elkins section of the Corridor H project. Keep checking this web site for future photo tour updates.


This section of Corridor H connects County Route 33 to U.S. 219. It was opened to traffic in January 2001. Looking east over Elkins from a completed section of Corridor H that connects County Route 33 to U.S. 219.


Looking from J.F. Allen Company's job across County Route 11 onto Polino Contracting Inc.'s job. J.F. Allen Company's job was completed in January 2001. The exit provides direct access to U.S. 219. Construction operations on the Polino Contracting Inc.'s job. The job is 1.5 miles long and is 91 percent complete.


Placing a drainage system and a culvert on the Polino Contracting Inc.'s job. A view of Kanawha Stone Company's bridge. This bridge will be 945 feet long and will cross County Route 1 and Pearcy Run. The workers in the lower right hand corner of the picture are building forms so that concrete can be poured to create a large column that will help support the bridge.


Looking east from the western abutment of Kanawha Stone Company's bridge. The contractor is constructing forms in which concrete will be poured to create the bridge's deck. Kanawha Stone Company constructing an access from County Route 1 to Corridor H. The deck is complete and the contractor is seen here constructing the concrete parapet.


Slide removal on J.F. Allen Company's project. Constructing the parapet on Bilco Construction Company's bridge. This bridge will be 575 feet long and will span Leading Creek and a Corridor H bicycle path.


Constructing deck forms on Bilco Construction Company's bridge. This work is 73 percent complete. Removing forms and smoothing the concrete parapet surface on the Bilco Construction Company's bridge.


A view of Vecellio and Grogan's bridge that spans U.S. 219. This bridge is 45 percent complete. Excavation on Vecellio and Grogan's project where an access road will be constructed.


A view of Vecellio and Grogan's bridge that spans U.S. 219 and County Route 7. This bridge is 55 percent complete and will be 279 feet long.


top of page

Route | Environment | Culture | Economics | Engineering | Safety | Press | Resource | Home
email us your comments or questions
Copyright © 2003 Corridor H, West Virginia Division of Highways. All Rights Reserved.