Elkins Construction Update - April 2002
The following is a photo tour of construction on the Elkins section of the Corridor H project. Keep checking the web site for future construction updates.


A view of Polino Contracting Inc.'s project from the intersection of Corridor H and U.S. 219. The final step on this job is to complete the finishing work. A view of Kanawha Stone Company's bridge. Bilco Construction Company, a subcontractor to Kanawha Stone Company, is finishing the work on the parapet walls of the eastbound lanes. The next step is to place a two-inch latex overlay on the deck of the eastbound lanes. The deck for the westbound lanes has been poured and the subcontractor is forming parapet walls for those lanes.


Two views of the access road connecting Corridor H to County Route 1.


A view of J.F. Allen Company's project. The final step for this segment is to complete the finishing work. A view of the slide on J.F. Allen Company's project that required the construction of a buttress to prevent future slippage.


A view of Vecellio and Grogan's bridge. PDK Construction Inc. is the subcontractor on this project and is placing guardrail along the bridge to the access road. Looking west from Vecellio and Grogan's bridge at Kerens. The contractor is preparing to pour the deck of the westbound lanes. A road that will connect Corridor H to U.S. 219 and County Route 7 can be seen to the left of the bridge.


A closer view of the access road that will connect Corridor H to U.S. 219 and County Route 7 at Kerens. Looking west from Vecellio and Grogan's project to J.F. Allen Company's project.




top of page

Route | Environment | Culture | Economics | Engineering | Safety | Press | Resource | Home
email us your comments or questions
Copyright © 2003 Corridor H, West Virginia Division of Highways. All Rights Reserved.